CST Articles

Article Details
Title Timetable: UK Studio
Date 4 February 2005
Category Production auditing

Timetable: UK Studio

KEY STAGES - TV UK STUDIO

The recommended tables are attached for shooting 3 different types of commercials i.e. Overseas, UK Location and UK Studio and are taken from the Producing Advertising Commercials report.

Although there is likely to be some variations against these ideals, they act as a useful guideline and if followed would result in better cost control.
Timetable: UK Studio
STAGETIMEWHO
Pre Production (15-17 weeks)
Creative brief to Agency with "ballpark"costStartClient/Agency
Present concept/script to client8-10 weeksAgency
Client approval of script/"ballpark" estimate1 weekClient/CST
Research, if required3 weeksClient
Client revisions1 weekClient
BACC Clearance of script1 weekAgency
Production (up to 18 weeks)
Formal Approval1 weekClient
Select Production Company (ies)1 weekAgency
Script meetings with Production Companies1weekAgency
Production Company Estimate to Agency1 weekAgency
CST to conduct audit1 week*CST
Final Estimate submitted and approved1 weekProd/Agency
Approve contract - 1st 50% invoicedClient/Agency
Casting1 weekProd/Agency
Pre Production meetingAll
1st 50% paidClient/Agency
Set Build1 weekProd
Shoot1 weekAll
Post ProductionVariableAgency
Directors CutProd/Agency
Agency CutAgency
Voice Over/Music etcAgency
Agency ApprovalAgency
Client approval1 weekClient
Video finishAgency
BACC approval1 weekAgency
Production Company paid 2nd 50%Client/Agency
Videos for SalesAgency/Client
Play-out to stations1weekAgency
TransmissionAgency
Reconciliation of costsafterAgency/*CST